Sixteen more AIIMS

Back
Phase-II, IV, V, VI & VII:-
 
Under these Phases, sixteen (16) additional AIIMS have been announced, out of which 16 AIIMS have been sanctioned / approved by Cabinet.
 
SL.       Phase    AIIMS Date of Cabinet Approval

Approved Cost  (cr)

Status and Progress of work
1
 Phase-II
 AIIMS, Raebareli (UP) 05.02.2009 [Revised cost estimates (RCE) was approved by EFC on 22.06.2017]  Rs. 823 cr

. Construction of medical college / hospital - Completed

 

2 Phase-IV AIIMS, Mangalagiri, Andhra Pradesh 07.10.2015 Rs. 1618 cr

Progress of work:

. Phase I - OPD block & residential complex: 100%

. Phase II – Hospital and academic campus: 99.5%

. IPD for COVID-19 treatment with COVID lab functional.

 

3 Phase-IV AIIMS, Nagpur (Maharashtra) 07.10.2015 Rs. 1577 cr

Progress of work:

 . Phase I - OPD block & residential complex: 100%

Phase II – Hospital and academic campus: 100%

. IPD for COVID-19 treatment with COVID lab functional.

4 Phase-IV AIIMS, Kalyani (West Bengal) 07.10.2015 Rs. 1754 cr

Progress of work:

. Phase I - OPD block & residential complex: 100%

. Phase II – Hospital and academic campus: 100%

5
Phase- IV
 AIIMS, Gorakhpur (Uttar Pradesh)  20.07.2016  Rs. 1011 cr

. Construction in EPC mode in progress (100%).

 

6. Phase- V AIIMS, Bathinda (Punjab) 27.07.2016  Rs. 925 cr

. Construction in EPC mode in progress (100%).

7. Phase- V AIIMS, Guwahati (Assam) 24.05.2017 Rs. 1123 cr

. Construction in EPC mode in progress (71.5%).

8. Phase- V AIIMS, Bilaspur (H.P) 03.01.2018

Rs.1471.04 cr

. Construction in EPC mode in progress (98%).

9. Phase- V

AIIMS,Madurai

 (Tamil Nadu)

17.12.2018 Rs. 1264 cr

. Site finalized at madurai.

. Pre-investment work in progress.

. Loan agreement with JICA signed on 26.3.2021.

. The detailed project schedule and the revised timelines are in process of approval.

. Appointment of PMC(project management consultant) in process.

10. Phase- V AIIMS, Darbhanga (Bihar)            15.09.2020 Rs. 1264 cr

.  Appointment of EA in process.

Encumbrance free land yet to be handed over by state govt.

11.

Phase- V

AIIMS, Samba (Jammu)

10.01.2019  Rs. 1661 cr

. Pre-investment activities in progress

. Construction work in progress (60%)

12. Phase-V AIIMS, Awantipora (Kashmir)  10.01.2019 Rs. 1828 cr

. Construction work in progress(20%).

13 Phase- VI

AIIMS, Deoghar

(Jharkhand)

16.05.2018 Rs. 1103 cr

Construction work in progress(86%).

14.  Phase- VI

AIIMS, Rajkot

(Gujarat)

10.01.2019 Rs. 1195 cr

 Pre-investment activities in progress.

. Construction work in progress(40 %).

 

15.  Phase - VII  AIIMS, Bibinagar   (Telangana)  17.12.2018  Rs. 1028 cr

Pre-investment work in progress.

Executing Agency for the main work appointed.

Design Consultant appointed.

. Tender awarded for main construction work.

 

16.  Phase- VIII

 AIIMS, Manethi

  (Haryana)

 28.02.2019  Rs. 1299 cr

Encumbrance free land yet to be handed over by state govt.