SL. | Phase | AIIMS | Date of Cabinet Approval |
Approved Cost (cr) |
Status and Progress of work |
1 | Phase-II |
AIIMS, Raebareli (UP) | 05.02.2009 [Revised cost estimates (RCE) was approved by EFC on 22.06.2017] | Rs. 823 cr |
. Construction of medical college / hospital - Completed
|
2 | Phase-IV | AIIMS, Mangalagiri, Andhra Pradesh | 07.10.2015 | Rs. 1618 cr |
Progress of work: . Phase I - OPD block & residential complex: 100% . Phase II – Hospital and academic campus: 99.5% . IPD for COVID-19 treatment with COVID lab functional.
|
3 | Phase-IV | AIIMS, Nagpur (Maharashtra) | 07.10.2015 | Rs. 1577 cr |
Progress of work: . Phase I - OPD block & residential complex: 100% . Phase II – Hospital and academic campus: 100% . IPD for COVID-19 treatment with COVID lab functional. |
4 | Phase-IV | AIIMS, Kalyani (West Bengal) | 07.10.2015 | Rs. 1754 cr |
. Progress of work: . Phase I - OPD block & residential complex: 100% . Phase II – Hospital and academic campus: 100% |
5 | Phase- IV |
AIIMS, Gorakhpur (Uttar Pradesh) | 20.07.2016 | Rs. 1011 cr |
. Construction in EPC mode in progress (100%).
|
6. | Phase- V | AIIMS, Bathinda (Punjab) | 27.07.2016 | Rs. 925 cr |
. Construction in EPC mode in progress (100%). |
7. | Phase- V | AIIMS, Guwahati (Assam) | 24.05.2017 | Rs. 1123 cr |
. Construction in EPC mode in progress (71.5%). |
8. | Phase- V | AIIMS, Bilaspur (H.P) | 03.01.2018 |
Rs.1471.04 cr |
. Construction in EPC mode in progress (98%). |
9. | Phase- V |
AIIMS,Madurai (Tamil Nadu) |
17.12.2018 | Rs. 1264 cr |
. Site finalized at madurai. . Pre-investment work in progress. . Loan agreement with JICA signed on 26.3.2021. . The detailed project schedule and the revised timelines are in process of approval. . Appointment of PMC(project management consultant) in process. |
10. | Phase- V | AIIMS, Darbhanga (Bihar) | 15.09.2020 | Rs. 1264 cr |
. Appointment of EA in process. . Encumbrance free land yet to be handed over by state govt. |
11. |
Phase- V |
AIIMS, Samba (Jammu) |
10.01.2019 | Rs. 1661 cr |
. Pre-investment activities in progress . Construction work in progress (60%) |
12. | Phase-V | AIIMS, Awantipora (Kashmir) | 10.01.2019 | Rs. 1828 cr |
. Construction work in progress(20%). |
13 | Phase- VI |
AIIMS, Deoghar (Jharkhand) |
16.05.2018 | Rs. 1103 cr |
. Construction work in progress(86%). |
14. | Phase- VI |
AIIMS, Rajkot (Gujarat) |
10.01.2019 | Rs. 1195 cr |
. Pre-investment activities in progress. . Construction work in progress(40 %).
|
15. | Phase - VII | AIIMS, Bibinagar (Telangana) | 17.12.2018 | Rs. 1028 cr |
. Pre-investment work in progress. . Executing Agency for the main work appointed. . Design Consultant appointed. . Tender awarded for main construction work.
|
16. | Phase- VIII |
AIIMS, Manethi (Haryana) |
28.02.2019 | Rs. 1299 cr |
. Encumbrance free land yet to be handed over by state govt. |